Each body: Barcelona shows the latest progress in the construction of the new Camp Nou, some details inside the stadium are still not completed

Football     3:45pm, 24 September 2025

According to "Every Physical Education", Barcelona shows the latest progress in the construction of the Camp Nou Stadium, and there are still some details inside the stadium that have not been completed.

Barcelona Club showed the media the latest status of the legendary stadium to the media on Tuesday as it awaits the first license and date for its return to the new Camp Nou. At present, the stadium lawn and the front two floors of the stands have been completely renewed. Barcelona operations director Joan Centels explained: "You can enter the game now and the audience can watch the game without barriers. This is the safest stadium in Spain."

Phase 1A, which includes the main stand with a capacity of 27,000 spectators and the south goal area, is waiting for a permit. The 1B phase, which increases capacity to 45,000 people, will be completed in a few weeks. Although the stadium is ready to be put into operation, the interior area still needs final trimming.

For example, cables are still hung in the corridor and the locker room has not yet been installed in a suspended ceiling. Eventually, the stadium will be equipped with three locker rooms. The spacious home dressing room has a swimming pool and multiple functional rooms, but is not yet completed. Currently, two more practical visiting team locker rooms have been built and the team is expected to temporarily use one of them.

Regarding the requirements the players may make for the locker room conditions, the club's agency vice chairman Maria Elena Fort said: "We have not discussed this with them yet. They should understand that this is a transitional period, and for us, the interests of members are the most important and everyone is making sacrifices."

In addition, the Center for Police Control (UCO) and the media area are still temporary. The Catalan police will set up a police station after the stadium is completed to monitor the situation in the entire stadium and its surroundings. Even the lighting system is temporary, as permanent lighting equipment will not be installed in place until the third floor stand is completed. Similarly, the scoreboard and media area will also be located above the VIP box and are still under construction.

With the completion of the first two stands, the club noted that the sight of the stands on the first floor was improved because of the adjustment of its inclination angle. This is just one of many improvements to the new Camp Nou. Other improvements include the installation of a 9km long guardrail on the second floor stand, and the evacuation time has been reduced from 8 minutes to about 4 minutes, thanks to the newly built huge and spacious entrances and exits.

At the same time, the third floor stand structure was raised to keep the stadium structure unchanged in 1957. Between these two levels, there will be a huge avenue surrounding the entire court. In the first phase 1A alone, more than 9 kilometers of fire-fighting pipes were laid, further improving safety.

At present, 475 VIP seats and expanded private rooms have begun to take shape, with the latter increasing from the original 147 to 296. 50 of these seats are part of VIP seats. In addition, the fan cheering area has been demarcated and moved to the south goal area for safety reasons, while the visiting fans will return to the third floor stand of the north goal area.

More data: The final building area will reach 251,000 square meters and the stadium height will be 80 meters. Currently, a 20-meter-high roof is missing, and this part of the project is scheduled to be completed between May and September 2027. The course capacity will add 5,000 seats, mainly due to the nearly sold-out VIP box ring area, with only some of the seats in the goal area on the north side not yet sold.